All-staff presentation occurs each month to communicate the scope, goals, activities and timeline of the project.

This month’s presentation has more detail on the content principles, navigation structure and content activities of the project.It highlights the teams across the University that have embraced the concept of understanding their audience’s needs and committed themselves to supporting the project.

Content Timelines and Deadlines:

For all content being created outside the project team

Deadline: 23 December 2016

Approval of content

When: happening now and into early January

Building pages in the CMS

When: happening now, with resources at their peak in January

CMS Content Freeze

19 – 23 December (all next week)