As works on our Central Courtyard Precinct redevelopment progress, services need to be changed or upgraded, with two important items of work happening in early December 2019.
Lincoln Building
A new fire booster set for the Lincoln Building will be installed and associated infrastructure, including digging a trench for underground pipework to be laid will be carried out.
Affected area:
The small carpark facing Wally’s Walk (adjacent Sir Christophe Ondaatje Avenue) will be unavailable – see below. For alternative disability parking see the accessibility map or email parking@mq.edu.au for assistance in locating a nearby alternative.
Time period :
From 6am Friday 6 December 2019 for approximately six weeks

MUSE 18 Wally’s Walk
The fire hydrant system will be changed over to a new set of water supply.
Affected area:
The whole building will be closed for 12 hours.
Time period:
Saturday 7 December 2019, 6am to 6pm
For any queries, email campusdevelopment@mq.edu.au.